New contractor sought for Papar Hospital upgrade in Sabah
KUALA LUMPUR: The upgrading of Papar Hospital has been delayed by 2,108 days following 11 extensions of time, the Dewan Rakyat was told today.
The upgrading of Papar Hospital in Sabah has been delayed by over six years due to 11 extensions of time, according to the Special Select Committee on Health. The original contractor's contract has been terminated, and a new contractor will be appointed through a new tender process. The extended delays were among the issues identified during a working visit to healthcare facilities in Sabah by the committee from August 17 to 21, which included Kota Kinabalu, Putatan, and Papar.
The Papar Hospital upgrade project has been plagued by significant delays and has faced various challenges, including shortages of healthcare personnel, suboptimal facility and infrastructure conditions, and a mismatch between capacity and increasing demand for healthcare services. Additionally, Queen Elizabeth Hospital, the state's main hospital and referral center, requires expansion of its capacity, human resources, assets, and support facilities due to growing workload and service scope.
Dental services also face capacity, service distribution, and manpower shortages, as demonstrated by Kota Kinabalu's record of 83,070 patient visits in 2025 despite only 11 dental chairs and numerous vacancies. The Health Ministry, along with the Finance Ministry and Public Works Department, is urged to prioritize critical asset and equipment repair, upgrading, maintenance, and replacement based on operational and safety requirements.
Furthermore, the committee recommends strengthening the recruitment, expansion, and distribution of healthcare personnel and specialist development, along with addressing specialist and subspecialist training shortages. The Health Ministry and Public Service Department are encouraged to review opportunities for specialist and subspecialist training, performance appraisal report requirements, career progression, and retention mechanisms for healthcare personnel, particularly in fields and areas with staff shortages.
The Health Ministry is also advised to enhance the digitalization of healthcare services through the provision of appropriate systems, hardware, networks, and information and communications technology infrastructure.