Sabah east coast power line expected to be reconnected tonight
A temporary tower was in place by noon yesterday, while conductor cable stringing is being carried out today as scheduled.
RANAU: Electricity restoration efforts in Sabah's east coast are expected to be completed tonight, according to Sabah Electricity CEO Yaakob Jaafar. The emergency restoration system (ERS) tower installation near the collapsed T313 tower in Kampung Sagindai is 70% complete, with five conductor cables already strung and another being installed to complete the first circuit.
Yaakob stated that the tower, built in 2007, collapsed due to erosion and weak foundation, exacerbated by sand embankments at the site and river currents. The 250km transmission line from Kota Kinabalu to Sandakan is typically inspected by helicopter every three months, with more frequent checks during the rainy season. Safety inspections are being conducted using a helicopter to ensure the line is re-energized safely.
The incident affected 153,599 registered Sabah Electricity consumers, with the utility aiming to restore electricity supply by December 2.
Rewritten by urgent.news; may contain errors — check the original.
Source: freemalaysiatoday.com