Power supply restoration in Sabah’s east coast reaches 60%
Sabah Electricity Sdn Bhd chief operating officer Riza Zalmee Ghazali says restoration works are now in the second phase.
On December 1, power supply in several districts along the east coast of Sabah has been partially restored, reaching 60% of normal capacity following a transmission tower collapse last Thursday. Sabah Electricity Sdn Bhd COO Riza Zalmee Ghazali informed reporters that the restoration efforts are now in the second phase, with temporary towers being installed under the emergency restoration system (ERS).
Nearly half of the region's electricity supply originates from the west coast, creating a deficit due to severed transmission lines. The incident, which occurred at 6:04am on December 1, severed two transmission circuits connecting the west and east coasts, disrupting power to eight districts and 153,599 consumers. Restoration of the transmission network in the east coast was completed by 6pm the same day, and all power generation units resumed full operation by 8pm.
However, Sabah Electricity is continuing rotational power rationing due to a shortage in available generation capacity. Riza appealed for public understanding and adherence to the rationing schedule, expressing optimism about completing full service restoration before December 1, should the weather remain favorable.
Rewritten by urgent.news; may contain errors — check the original.
Source: freemalaysiatoday.com