Anwar: Sabah Electricity must speed up power restoration
KOTA KINABALU: Sabah Electricity must speed up restoration works to restore power to more than 150,000 people in eight east coast districts affected by a transmission tower collapse in Ranau, says Prime Minister Datuk Seri Anwar Ibrahim.
Prime Minister Anwar Ibrahim has urged Sabah Electricity to expedite the restoration of power to Sabah’s east coast, which has now entered its third day. The disruption has affected up to eight districts following the collapse of a transmission tower in Ranau due to heavy rainfall. Anwar emphasized that every hour during this crisis is crucial for the affected communities, especially children preparing for the Sijil Pelajaran Malaysia (SPM) examination.
He requested Sabah Electricity to prioritize schools, examination centers, and critical public facilities in the restoration process and to consider providing temporary electricity supply.
The transmission tower T313 collapsed on Thursday after the foundation was washed away by the heavy rain, which initially cut power to 153,599 consumers in the affected districts. Sabah Electricity has stated that they aim to fully restore the 275kV east coast grid by December 2, with supply being rationed in three-hour shifts until Monday. As of yesterday, power had been restored to 57% of the affected areas, with a temporary emergency tower set to be erected in Ranau.
The Sabah Education Department has confirmed that all 42,808 SPM candidates in the state have not been impacted by the outage. This current blackout follows a similar incident in September 2025, which affected six east coast districts and 230,000 consumers. In June, Anwar had announced the first phase of a RM198 million project to enhance Sabah’s power transmission infrastructure.