KOTA KINABALU, Nov 27 — The components of the Emergency Restoration System (ERS) temporary tower arrived at the site of...
Six days are needed to fully restore Sabah's east coast electricity grid, following a transmission tower collapse in Ranau, according to Sabah Electricity Sdn Bhd. The tower collapse was caused by riverbank erosion along Sungai Liwagu, exacerbated by strong currents following heavy rainfall. The restoration is expected to be completed by December 2, with the affected districts experiencing power disruption.