Six days to restore Sabah east coast grid, riverbank erosion caused tower collapse
KOTA KINABALU: Sabah Electricity Sdn Bhd (Sabah Electricity) is targeting six days to fully restore the 275kV transmission grid supplying Sabah's east coast after a transmission tower collapsed in Ranau early today.
Six days are needed to fully restore Sabah's east coast electricity grid, following a transmission tower collapse in Ranau, according to Sabah Electricity Sdn Bhd. The tower collapse was caused by riverbank erosion along Sungai Liwagu, exacerbated by strong currents following heavy rainfall. The restoration is expected to be completed by December 2, with the affected districts experiencing power disruption.