MP's Vindhya Irrigation Projects Worth ₹9,617 Crore Face Years Of Delays; 16 Schemes Incomplete, Costs Escalate Despite Repeated Deadline Extensions
Bhopal (Madhya Pradesh): Despite expenditure of Rs 3,430.56 crore, 16 irrigation projects across Vindhya remain incomplete, with their escalated cost reaching Rs 9,617.92 crore. Several projects have missed deadlines dating back to 2016. Records of the Ganga Kachar water resources department, Rewa, show revised approvals and separate contracts for unfinished works. Departmental sources alleged…
In the Vindhya region of Madhya Pradesh, 16 irrigation projects that cost Rs 3,430.56 crore to date have stretched to an estimated total of Rs 9,617.92 crore due to delays and cost escalations. Some of these projects, including Teonthar Flow Scheme, Teonthar Micro Irrigation, Naighadi, Ramnagar, Gond Naighadi's two units, Ramnagar Micro Irrigation, Gond, Bahuti Main Canal, Bahri Canal and Semaria Micro Irrigation, have missed deadlines dating back to 2016.
The Teonthar Flow Scheme, originally set to complete by September 30, 2016, is now projected to finish by December 31, 2025, while the Teonthar Micro Irrigation is slated for completion by July 2026. Similarly, Naighadi's two units, originally due by September 2020, have a new deadline of June 2026.
The administrative approvals for these projects have also escalated. For instance, the Teonthar Flow Scheme saw its administrative approval rise from Rs 490.84 crore to Rs 570.51 crore, while the Majhgawan Branch Canal's ballooned from Rs 264.34 crore to Rs 285.1 crore.
However, the heightened costs and delays have also led to allegations of irregularities. Departmental sources have accused certain companies of receiving tender clearances despite not meeting eligibility criteria. The Bahuti Main Canal, for example, was declared complete and payments released despite unfinished work.
Executives attribute these challenges to issues like land acquisition, forest clearances, the impact of Covid-19, and pending approvals. Despite these hurdles, the departmental sources believe the projects will still be completed by the revised timeline of 2027.
Rewritten by urgent.news; may contain errors — check the original.