Contractor on KATH Mother and Baby unit project awaits payment as materials expire
The Liaison Officer for Contracta, construction firm for the stalled Komfo Anokye Teaching Hospital (KATH) Mother and Baby Unit, Emmanuel Danso, has expressed worry persistent non-payment to the contractor.
The Maternity and Children’s Block project at Komfo Anokye Teaching Hospital (KATH) has been halted due to unpaid claims from the contractor, casting doubt on the timely completion of this vital healthcare facility. This situation recently came to light during an inspection by the Parliamentary Select Committee on Health, chaired by Dr. Mark Kurt Nawaane.
The project manager revealed that, while procurement is 75% complete and construction stands at 56%, the work was suspended due to unpaid contractor claims. These interruptions have resulted in delays and added expenses, as well as concerns about the warranty of materials and the condition of the site. Notably, the contractor has continued to maintain the site during the suspension periods.
Essential materials such as air-conditioning units, electrical components, and building façades have already been procured and are awaiting the contractor's return. The project manager stated that the contractor is awaiting the necessary payments and further stakeholder engagements before resuming work. The Maternity and Children’s Block is crucial for expanding specialized maternal and pediatric healthcare services at KATH, one of the main referral hospitals in the Ashanti Region.
The hospital’s CEO emphasized the importance of this facility, which will enhance healthcare delivery for mothers, children, and families. The Committee recognized the significance of this project and urged stakeholders to resolve payment issues and facilitate the contractor's return to the site.