Tasmania's EPA is worried about the extent of AI data centre company Firmus's planned diesel generator use, saying it is much more than initially disclosed.
The Tasmanian Environmental Protection Authority (EPA) expressed concern that Firmus Technologies plans to utilize diesel generators more frequently than previously disclosed. The EPA has subsequently applied to join Firmus's appeal before the Tasmanian Civil and Administrative Tribunal (TASCAT), where Firmus seeks to have conditions on generator use lifted.
A Firmus submission to a federal joint select committee on AI revealed additional renewable energy infrastructure intended to power its data centres, which may not necessarily be constructed within Tasmania. The EPA urged a tribunal to hear its concerns, as Firmus's generator usage plans exceed the originally declared limits. Earlier this year, the George Town Council approved Firmus's proposal for a 288-megawatt data centre in Tasmania's north, contingent on the EPA's approval of certain conditions, particularly limiting the use of 276 on-site diesel generators to emergencies or routine inspections.
Firmus appealed this condition, arguing it intended to use the generators primarily for augmenting mains electricity supply to mitigate curtailment, manage energy security, and maintain operational reliability during periods of energy market stress. The EPA board submitted that Firmus's recent appeal indicated it planned to employ the generators in more circumstances than initially believed, potentially altering the environmental risk profile associated with the activity.
Upholding Firmus's appeal could permit the activity to proceed without proper environmental assessment, possibly leading to harm and necessitating EPA enforcement action.
Rewritten by urgent.news; may contain errors — check the original.
Source: abc.net.au