Chong questions LCS handover as technology, threats evolve
Kampar MP says changing technology and security threats could make the LCS’s planned capabilities outdated by the time they are fully operational.
Kampar MP Chong Zhemin queried the utility of the littoral combat ships (LCS) Malaysia ordered, questioning whether they will remain relevant by the time they become fully operational around 2035, given the 24-year gap since the project's approval in 2011. The Auditor-General's Report 2/2026 revealed that the navy's first LCS 1 might not reach full operational capability until December 2035.
During a debate in the Dewan Rakyat, Chong pointed out the potential evolution of technology and security threats over two decades, questioning if the LCS capabilities would align with contemporary operational needs. He argued that the ship was purchased to address current threats, not yesterday's, and expressed concern over the ship potentially being designed for obsolete threats when the threat landscape has shifted.
Chong urged the government to present a comprehensive recovery plan, including the identities of suppliers, timelines, and budget details. He also directed questions towards Deputy Prime Minister Ahmad Zahid Hamidi, who was the defence minister during the initial procurement decisions in 2010 and 2011, demanding an explanation for his role in the decision-making process.
Chong demanded accountability for any misconduct, irrespective of position or political inclination. He advocated for a royal commission of inquiry into the LCS project, citing that the ship might be handed over without complete training and weapon systems, potentially not achieving full combat capability until December 2035. The audit highlighted that trials and commissioning were delayed, and five complementary contracts for weapons and support systems remain incomplete.
The audit identified the most critical issue as the delayed delivery of surface-to-surface missiles, which experienced two delivery delays this year before being suspended due to the supplier's export license suspension. Furthermore, the LCS project, initially estimated at RM9 billion, has ballooned to RM11.22 billion after delays and cost overruns, with only five vessels being delivered instead of the originally planned six.
The project's timeline has also been significantly delayed, with the first ship now expected in 2029, far beyond the initial 2019 target.