LKAN kesan banyak kelemahan dalam projek Pan Borneo Sabah
Arahan perubahan bernilai RM513.99 juta diluluskan melebihi had kuasa kelulusan ditetapkan,manakala 19 pakej projek dimulakan sebelum laporan EIA lulus.
The Lebuhraya Pan Borneo project in Sabah remains unfinished despite being planned for 10 years, despite a change in management from a construction partner to the Ministry of Major Projects in September 2019. According to the Auditor General of Malaysia (LKAN), the project suffers from various weaknesses in design and execution, beyond breaches of guidelines and regulations.
As of March 31, the project is still incomplete, with the foundation site not fully prepared, with a total payment of RM144 million not yet made and 99 structures not demolished for Phase 1A of the project. For Phase 1B, a payment of RM84 million is still unclear, while 3,360 structures need to be demolished. The report also found multiple change orders amounting to RM513.99 million approved beyond the authorized approval power, while 19 project packages were initiated before the Environmental Impact Assessment (EIA) report was approved.
Additionally, there is a dispute over the cost of piling 13 items under 10 change order directives worth RM60.87 million, according to the report. The report emphasizes that change order approvals should be strictly based on contract terms, while contractors must be guided to implement the change orders while resolving disputes.
In terms of contract management weaknesses, the government is forced to bear the difference amounting to RM32.95 million from the initial cost of works, insurance, and contractor payments. Additionally, RM164.64 million in payments was made irregularly due to late contract document preparation. The Auditor General of Malaysia also recommends improving the project's operation standard procedures and enhancing monitoring of the entire design and execution of the project.
Pan Borneo in Sarawak is almost complete, with 10 work packages ready and Lambir package reaching 99.9% completion. Overall, the project has a positive impact by stimulating economic and social activities along the project corridor, while RM18.839 billion out of the RM18.864 billion allocated has been spent as of March 31. However, the report states there are still some weaknesses and shortcomings in project management and contract handling.
The KKR and State Works Department have not yet filed a claim of RM1.78 billion against four utility companies regarding the relocation and replacement of various utility infrastructure. The rest area stops Julau and Sungai Arip, each costing RM2.38 million and RM17.8 million, respectively, are also still unused.
Written by urgent.news from Free Malaysia Today's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.