Kemajuan projek LCS lewat 7.55%, menurut LKAN
Jabatan Audit Negara memaklumkan audit dilaksanakan secara interim untuk menilai pengurusan projek LCS dari aspek kemajuan fizikal dan kewangan, pengurusan kontrak serta pembayaran berdasarkan terma kontrak dan peraturan berkuat kuasa.
Kementerian Pertahanan is urged to enhance monitoring of the advancement of the Surface Combatant Vessel project, including the appointment of responsible personnel and timeframes for critical issues until the project is completed successfully. As of June 25, the delay in the advancement of the Surface Combatant Vessel (LCS) project is 7.55%, with a delay ranging between 30 to 108 days, according to the National Audit Department (JAN).
In a statement regarding the National Chief Auditor's Report 2/2026 today, JAN announced that the delay could jeopardize the early handover of LCS 1 scheduled for August 26 or the revised deadline of August 26. If the handover is not completed on both dates, LCS 1 will be delivered without achieving full capabilities due to unrefined training and weapon systems.
The full readiness of the LCS project depends on the Supplementary Contract which can only be completed by December 2035, encompassing the final stages of the Main Contract on April 25, 2030. The delay in the handover of LCS 1 impacts the handover timelines for LCS 2 to LCS 5. JAN announced that interim auditing will be conducted to assess the management of the LCS project from both physical and financial aspects, contract management, and payments based on contract terms and governing powers.
The audit will also take into account the opinions of the National Treasury Auditor (PAC) through its Parliamentary PAC Report dated October 9, 2023 to enable JAN to conduct an audit of the LCS project before the handover of LCS 1 to the Chief of the Navy and present the audit findings in Parliament. JAN assured that for the project to be prepared and handed over at the readiness level, the Malaysian Defense Ministry set a realistic remedial plan to ensure all critical Contract Main and Supplementary Contract activities are adjusted according to the LCS handover schedule.
Additionally, the ministry assured that any transfer of the vessel will be subject to obligations, completion timeframes, and contractor responsibilities clearly defined until the vessel reaches operational capability. The Malaysian Defense Ministry is urged to enhance monitoring of the project advancement, including the appointment of responsible personnel and timeframes for critical issues to ensure successful completion of the project.
Written by urgent.news from Free Malaysia Today's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.
This story
This is one outlet's version. Read the fullest account.
- LKAN kesan banyak kelemahan dalam projek Pan Borneo Sabah freemalaysiatoday.com