Power approval set to delay Oracle's Wisconsin AI datacenter
Grid connection awaits regulatory approval, putting planned 2027 customer delivery at risk
Oracle's planned AI datacenter in Wisconsin may not meet its 2027 target due to pending regulatory approval for its transmission infrastructure. Aterio, a research company, warns that Project Lighthouse, developed by Vantage in Port Washington with Oracle as tenant, faces a significant risk of delay beyond Oracle's stated capacity delivery window in the second half of 2027.
Oracle has reportedly sent a force majeure notice to a subsidiary developing Project Jupiter in New Mexico, seeking to defer payments if the campus fails to open as planned. The delay is attributed to American Transmission Company's (ATC) pending application to the Public Service Commission of Wisconsin (PSC) for approval of the grid connection needed for the campus to operate.
Aterio suggests the earliest scenario could see partial power availability by October 2027 and full supply by October 2028, although these dates are considered highly unlikely.
Written by urgent.news from The Register Science's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.
Other reports of this story
- Power approval set to delay Oracle's Wisconsin AI datacenter theregister.com