Tung Chung housing project concrete fails test again

The Housing Authority (HA) said on Tuesday that individual concrete test samples from Block 2 of a public housing project in Tung Chung had failed to meet contractual requirements, the latest issue to affect the estate. The authority had previously said that components in Blocks 3, 4 and 5 of the same project in Area 42 required further review and testing. In response to media queries, the HA…

The Housing Authority (HA) disclosed on Tuesday that concrete test samples from Block 2 of Tung Chung's public housing project failed to satisfy contractual specifications. This is the most recent issue impacting the estate, with earlier reports indicating components in Blocks 3, 4, and 5 needed further examination. In response to inquiries, the HA instructed the contractor to halt concrete pouring, extract concrete cores for analysis at an accredited lab, and await test results.

Of the 12 samples analyzed, representing roughly 17 percent of the total, strength results ranged from 23 to 66 percent higher than the standard, all meeting design and contractual requirements. The HA's engineering department will decide if the concrete strength of affected structural elements needs reviewing after all test results arrive.

If a review is required, the contractor must submit a remedial plan for HA approval before resuming concrete work. Expected completion of full test results is September 25, with the HA anticipating minimal impact on project progress.

Written by urgent.news from RTHK News's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.

Also reported by 1 other outlet

Read the original at news.rthk.hk →

More in World

More from Tuesday 22 September →