Tepco delays completion date of Niigata nuclear plant’s anti-terrorism facility
The contracting company informed Tepco that construction needs to be extended by more than a year due to factors including labor shortages.
Tokyo Electric Power Company Holdings has announced it will reconsider its schedule for finishing an anti-terrorism facility at the Kashiwazaki-Kariwa nuclear power plant's No. 7 reactor in Niigata Prefecture. The construction company informed Tepco that the project will need to extend by over a year due to factors such as labor shortages.
This delay further pushes back the reactor's restart after Tepco previously postponed the facility's completion from October 2025. No new completion target has been set yet. Another anti-terrorism facility for the plant's No. 6 reactor, which restarted in January, remains unfinished and must be completed by April 2031 for the reactor to continue operating.
Tepco's manager, Takeyuki Inagaki, stated that the company aims to finish the facility for the No. 7 reactor by April 2031. New nuclear plant safety standards, introduced following the 2011 Fukushima disaster, require the installation of antiterrorism facilities within five years of reactor construction plans' approval. The initial deadline for the Kashiwazaki-Kariwa No. 7 reactor was October 2025, but Tepco delayed the completion to August 2029 due to longer-than-expected regulatory reviews for the reactor's restart. Consequently, Tepco chose to restart the No. 6 reactor ahead of the No. 7 reactor.
Rewritten by urgent.news; may contain errors — check the original.
Source: japantimes.co.jp