Mumbai's First Major Waste-To-Energy Plant 93% Complete, BMC To Start Trial Runs In December

Mumbai's first large-scale waste-to-energy facility at the Deonar dumping ground is reportedly close to being completed.The Brihanmumbai Municipal Corporation (BMC) is planning to commence trial operations for the plant in December. The Rs 648-crore project is expected to become operational in early 2027 and will convert municipal waste into electricity, The Times of India reported. The…

Mumbai's First Major Waste-To-Energy Plant 93% Complete, BMC To Start Trial Runs In December

Mumbai's first large-scale waste-to-energy plant at the Deonar dumping ground is nearing completion. The Brihanmumbai Municipal Corporation (BMC) aims to start trial operations in December. The Rs 648-crore project is set to become fully operational in early 2027 and will convert municipal waste into electricity. Currently, the construction is 93% complete.

Initially scheduled for October 2025, the project faced delays due to logistical issues, a rise in the power generation capacity, and pending legal clearances. The facility is designed to process 600 tonnes of fresh municipal solid waste daily and generate up to eight megawatts of electricity. After the trial phase, which will last one to two months, the BMC will seek approval from the Maharashtra Electricity Regulatory Commission (MERC) to sell the generated electricity.

The power is expected to be supplied to Adani Electricity, and the revenue generated will be credited against the civic body's electricity bills. The exact tariff has not yet been fixed and could range between Rs 5 and Rs 10 per unit. However, the plant won't be able to process the accumulated legacy waste found at Deonar; it can only handle fresh municipal waste.

Nearly a million tonnes of old waste had to be safely relocated and stabilized before construction could begin. To manage this legacy waste, the BMC has enlisted Navayuga Engineering Ltd to undertake bioremediation, handle disposal of processed material, and reclaim 110 hectares of land at the site. Currently, Mumbai operates two BMC-run C&D waste recycling facilities in Dahisar and Shilphata, each with a capacity of 1,200 tonnes per day.

Since their inception in 2024, these plants have collectively handled approximately 3.3 lakh tonnes of debris, including nearly 2.11 lakh tonnes of material.

Rewritten by urgent.news; may contain errors — check the original.

Source: freepressjournal.in

Read the original at freepressjournal.in →

Report a problem with this story

More in World

More from Friday 27 November →