We tested agile "85% delivery dates" on 53 public Jira projects. Here is what held up.

Written by MV2 of Munim, Inc. The study, the code and this post were made with AI agents working in my name; no human expert has reviewed the study yet. Everything below is reproducible from the repo. Many teams now promise delivery dates with a throughput Monte Carlo: resample how many items you finished on past days, simulate thousands of futures, and quote the date you hit "with 85%…

A recent study examined the accuracy of agile "85% delivery date" predictions across 53 public Jira projects. The research found that these predictions tended to be overly optimistic. When applied to a diverse set of 25 Apache projects, the 85% forecasts proved accurate approximately 80% of the time, falling short of the target in 20% of cases.

This trend was replicated across 28 projects drawn from MongoDB, Atlassian, Red Hat, and Jenkins sources, where 85% predictions also fell short in 23 out of 28 instances. The study suggests that the discrepancy stems from two main factors: the inherent optimism in the forecasting method, which tends to overestimate success rates, and real-world variability in team performance that can disrupt initial projections.

The authors developed a tool called Ship Odds to address this issue by recalibrating predictions based on a team's historical performance data, aiming to narrow the gap between forecasted and actual outcomes. However, while recalibration improved the accuracy of the 85% predictions for some teams (increasing from 79.3% to 84.7% on Apache projects and 83.6% to 86.6% on newer trackers), it did not uniformly enhance the odds across all cases.

Specifically, the correction mechanism did not lead to significant improvements in the Brier score, a measure of probability accuracy, in most instances. The authors acknowledge that while their findings highlight the potential for improved accuracy through data-driven adjustments, the effectiveness of recalibration varies depending on the specific team dynamics and project characteristics.

They encourage teams to critically evaluate their own forecasting accuracy and consider the provided tools and methodologies to refine their delivery date predictions more effectively.

Rewritten by urgent.news; may contain errors — check the original.

Source: dev.to

Read the original at dev.to →

Report a problem with this story

More in Tech

How to Verify a Hosting Provider Before You Buy

Originally published on my blog — read it there with the full context, code and updates . Every hosting provider's homepage is a list of promises: "in business since 2005" , "guaranteed uptime"…

  • Examine domain age vs provider's claimed "since" date
  • Scrutinize Acceptable Use Policy (AUP) for prohibited activities
  • Conduct reputation check using third-party sources like Trustpilot

Amazon product search as JSON: prices, ratings and sponsored flags in 20 lines of Python

Amazon's official Product Advertising API requires an approved Associates account and ongoing qualifying sales. If you are building a small price monitor, competitor tracker, or catalog lookup tool…

  • Amazon Product Advertising API provides structured JSON search results
  • POST request to /amazon/search endpoint with search term and API key
  • Retrieves product details like prices, ratings, and sponsored flags

Renaming a Database Column Without Downtime

My earlier posts kept saying "expand and contract" without ever showing it end to end. This one does. I'll rename users.fullname to users.display_name on a live PostgreSQL database, one safe step at a…

  • Add new column displayname with nullable type during migration
  • Dual-write old fullname and new displayname columns for data consistency
  • Drop old fullname column after verifying displayname consistency

More from Wednesday 25 November →