Mumbai Coastal Road North Project: BMC Sets Strict Deadlines For Versova-Dahisar-Bhayander Link Road, Targets Dec 2028 Completion
Mumbai, November 25, 2026: With construction of the Mumbai Coastal Road Project (North), connecting the Versova-Dahisar-Bhayander Link Road (VDBLR), gathering pace, the civic authorities have turned up the heat on contractors, issuing strict deadlines and ordering parallel execution of critical works to prevent delays across the seven project packages. Additional Municipal Commissioner (Projects)…
On November 25, 2026, Mumbai's civic authorities, led by Additional Municipal Commissioner (Projects) Abhijeet Bangar, enforced strict deadlines on the Mumbai Coastal Road Project North, specifically for the Versova-Dahisar-Bhayander Link Road (VDBLR) construction. The project encompasses seven packages, with the primary goal of reducing traffic congestion and travel time.
Bangar visited the project site and scrutinized Package A at Kavthe Creek, demanding increased machinery deployment and simultaneous execution of critical works like the temporary access road and perpendicular temporary bridge. At the Lokhandwala interchange, he set a 100-day deadline for piling work to clear the way for the main bridge.
In Package B, under the Mindspace-Malad interchange, Bangar ordered simultaneous piling progress of seven directions for the 4,000-meter Temporary Access Bridge (TAB), targeting a minimum of two meters per day construction rate. Package C involved initiating piling at Raheja's proposed retrieval shaft location.
At Charkop, excavation on the launching shaft reached 10 meters, with a daily progress rate of 1,350 cubic meters. The shaft is expected to be completed by March 31, 2027, followed by the Tunnel Boring Machine assembly from April 1. The first tunnel excavation is planned for May 31, with the second tunnel excavation scheduled for July 31, 2027. The first Tunnel Boring Machine is projected to reach the Malad retrieval shaft by July 2027.
Bangar instructed officials to ensure the shaft readiness before the machine's arrival, emphasizing that delays or poor coordination must not disrupt the tunnelling schedule. The 20-kilometer VDLR, costing Rs 16,621 crore, aims to ease congestion in the region, including a 5.6-kilometer elevated road (45 meters wide) connecting Dahisar to Bhayander for Rs 3,304 crore to further improve traffic flow.