MPs Question KPLC Over Contractor Performance and Delays in Last Mile Connectivity Project
The National Assembly Departmental Committee on Energy and Petroleum has questioned the Kenya Power and Lighting Company (KPLC) over procurement procedures, contractor performance and changes to project sites under the Last Mile Connectivity Project. During an oversight meeting with KPLC management, MPs raised concerns about the award of contracts to firms previously linked to poor [...] The post…
The National Assembly's Energy and Petroleum Committee has scrutinized Kenya Power and Lighting Company (KPLC) regarding the Last Mile Connectivity Project. During a meeting with KPLC officials, MPs expressed concern over the company's procurement methods, contractor performance, and adjustments to project locations. Committee Chair David Gikaria urged KPLC to enhance its due diligence measures to ensure contractors have the necessary technical and financial capabilities to finish public works.
He emphasized that the committee's oversight is not to interfere with KPLC's daily operations but to ensure judicious use of public funds and timely delivery of electricity infrastructure.
MPs also questioned alterations to proposed electricity connection sites within the Last Mile Connectivity Project. They were especially concerned when communities had already been surveyed and residents had submitted identification documents for connection. The MPs urged better collaboration between KPLC and local leaders to prevent affected communities from being overlooked without clear explanations.
KPLC management admitted to delays in implementing Phase Four of the project, which was originally set for completion by October 2026. The utility informed the committee that the new finish date is now June 2027. KPLC cited administrative and financial issues, including delayed fund disbursement and tax exemption extensions, as contributing factors to the delays.
The utility stated that its request for the 2026/2027 project allocation was submitted in July 2026, but approval from the National Treasury did not come until late October. This delay impacted the payment processing to contractors, thus hindering project progress. Furthermore, the extension of the French Development Agency (AFD) financing agreement, granted on November 18, 2026, temporarily affected tax and import duty exemptions for project materials at customs, adding to the implementation challenges.
To expedite the project, KPLC established a dedicated bank account for payments under 26 active Engineering, Procurement and Construction (EPC) contracts, which include 17 EU-funded lots worth Sh17 billion and nine EIB-funded lots valued at Sh7.9 billion. So far, Sh4.4 billion, or 68 percent of the disbursements, have been paid via this account.
The committee stressed the necessity of stronger procurement oversight, improved coordination with elected officials, and timely fund release to prevent delays in providing electricity to communities targeted by the Last Mile Connectivity Project.