Construction underway on temporary transmission towers for Eyre Peninsula

Four temporary towers will be installed on the state's Eyre Peninsula, to bring transmission services back to the region after storm activity last week.

Construction underway on temporary transmission towers for Eyre Peninsula

Construction is currently underway on four temporary transmission towers on the Eyre Peninsula, aimed at replacing those damaged by recent storm activity. By Friday, these temporary structures are expected to be operational. The permanent replacement towers are projected to take up to a year to complete. The southern part of the Eyre Peninsula is anticipated to reconnect to the national electricity grid by Friday morning, after two transmission towers were downed and a third severely damaged during last week's severe weather.

Over 20,000 properties on the peninsula and West Coast lost power on Thursday during the storm, and while temporary towers construction has begun, operators indicate it may take a year to install the permanent structures. The affected towers were situated on a farm at Wharminda, along a 270-kilometre transmission line between Port Lincoln and Cultana.

The electricity transmission operator, ElectraNet, stated that local generation restored power for Port Lincoln and nearby areas on Thursday night, necessitating network reconfiguration to restore services to other parts of the Eyre Peninsula. Once erected, the four temporary towers will undergo testing before re-energization, which would restore transmission services from Cultana to Port Lincoln.

ElectraNet CEO Simon Emms expressed optimism that services would be back in operation by early Friday. The temporary towers are being positioned on either side of the existing line route, with the current line laid flat and subsequently erected today. ElectraNet maintained that the temporary towers adhere to the same standard as the existing line.

Following the storm, on Wednesday, ElectraNet reported that the three transmission towers were damaged by a localized and severe wind event, and they are confident the towers meet the required strength standards. The design of the towers was independently checked, and ElectraNet built and tested a test tower to destruction to ensure compliance.

ElectraNet is committed to conducting a comprehensive investigation into the incident. Following the storm, ElectraNet had suggested the towers likely fell due to a "one-in-2,000-year weather event," a claim the SA government intends to investigate. ElectraNet has advised Port Lincoln residents to keep rooftop solar inverters off until further notice to prevent generator issues before the transmission line is restored.

Rewritten by urgent.news; may contain errors — check the original.

Source: abc.net.au

Read the original at abc.net.au →