A Power Provider for Meta Urged Regulators to Exempt Data Center Plants From Acid Rain Rules
Before the EPA recommended waiving acid rain regulations for certain data-center power plants, it met with industry players—including Williams, a gas power provider for Meta data centers.
The oil and gas infrastructure firm Williams is urging regulators to exempt data center power plants from Acid Rain Program rules, as the Trump administration eases environmental requirements for these facilities. According to Joseph Goffman, a former EPA assistant administrator, the administration is either explicitly or implicitly removing layers of regulatory protections for data centers.
Williams spokesperson Alex Schott stated that the company is committed to developing energy solutions while prioritizing environmental protection, but declined to comment on Meta's involvement. In July, the EPA issued new federal guidance for states regarding participation in the Acid Rain Program, recommending that "islanded" power plants, which are increasingly used by data centers, be exempt from the program.
Williams was among three private companies that requested guidance on the program. In a letter to the Utah Department of Environmental Quality, Williams director of permitting Steve Hall argued that the current regulatory uncertainty surrounding power plants solely powering data centers poses obstacles for data center development in the United States.
He believed that his power plants were not subject to the Acid Rain Permit program, as it was never intended to apply to sources that do not sell power to the public grid. The EPA's July announcement was in line with White House orders to encourage data center developers to build their own power, avoiding increased utility rates for consumers.
However, data center developers are also opting for private power, which often results in higher emissions than on-grid alternatives. Williams, a leading oil and gas infrastructure company, has been a provider for Meta's data center projects, including four in Ohio and one in Utah. The EPA confirmed that Williams requested regulatory guidance for these Ohio and Utah projects, which are around 500 megawatts each.
Williams submitted a proposal to exempt behind-the-meter data centers from Acid Rain Program requirements in September 2025, arguing that the long permit timelines are not feasible given the urgent need to install and operate gas-fired generation for AI data centers.
Rewritten by urgent.news; may contain errors — check the original.
Source: wired.com