6 qualify for Ukraine's 1.5 GW new generation tender

The commission running the tender for building new generating capacity and carrying out demand management measures has named six qualified participants.

6 qualify for Ukraine's 1.5 GW new generation tender

Six entities have been selected to participate in Ukraine's new 1.5 GW generation tender, announced in the minutes of the commission's November 12 meeting. The six qualified bidders are Ukrnafta, Odesa CHP, Dniprovska Combined Heat and Power Plant, Kryvorizka Combined Heat and Power Plant, KGG-Energo, and Energysoft. All proposals met the qualification requirements, according to the commission's findings.

Energysoft, a Kyiv-based entity with a UAH 1,000 charter capital, is ultimately owned by Yevheniy Vorobiov, who holds a 90% stake. KGG-Energo, registered in Kremenchuk in 2006, has a 52% ownership stake belonging to Valentyna Volkonska. The tender allocates a 250 MW quota to the Kyiv and Cherkasy regions, while the Sumy, Kharkiv, and Poltava regions collectively receive 872 MW, Dnipropetrovsk gets 283 MW, and Odesa receives 100 MW.

The new facilities must have a minimum operating life of 20 years or 100,000 hours, and meet technical requirements to aid in balancing Ukraine's power system. Capacity must be at least 10 MW. The commission, led by First Deputy Energy Minister Artem Nekrasov, has guaranteed a total capacity of 78.1 MW in the first stage of the tender, which concluded late 2025.

Starting in the second stage, Ukrenergo will provide a market premium mechanism support when electricity prices in the morning and evening peaks fall below the tender-set price, up to 27.92 euro cents per kWh. This support will last seven hours daily during autumn and winter, and five hours in spring and summer. Ukrenergo's management board member Ivan Yuryk explained that the three-year payback period for investors is calculated, but due to the need for second-level protection, the guaranteed price support period is set at five years. The winning projects must be operational within 20 months of the tender announcement.

Rewritten by urgent.news; may contain errors — check the original.

Source: en.interfax.com.ua

Read the original at en.interfax.com.ua →

Report a problem with this story

More in World

More from Monday 23 November →