Now, Maharashtra Pollution Control Board issues stop-work directions to Adani project
The Maharashtra Pollution Control Board (MPCB) has ordered Adani Green Energy Limited's Tarali Pump Storage Project to halt work in Sawarghar village, Satara district. The company had conducted excavation and development work without obtaining the required permissions or environmental clearance. The MPCB granted the project a "Consent to Operate" but emphasized the need for adequate pollution control measures.
The 1,500-megawatt Tarali PSP is planned on the Tarali dam reservoir, covering 150.74 hectares of non-forest land. Adani Green Energy maintains that all necessary permissions were secured and that the project does not impact forests or wildlife.
Rewritten by urgent.news; may contain errors — check the original.