Mumbai Infra Update: BMC Prepares To Launch Girders For Bandra-Dharavi Bridge, 10-Lane Project Enters Crucial Phase
Mumbai, November 20, 2026: The Bandra-Dharavi bridge reconstruction project has entered a crucial phase, with the BMC preparing to launch girders for a new crossing over the Mithi River. The development marks a significant step towards expanding the existing bridge to 10 lanes and improving traffic connectivity between Bandra Kurla Complex (BKC), Dharavi and Mahim Causeway. Rs 204 Crore Project…
On November 20, 2026, the Mumbai Municipal Corporation (BMC) is set to commence the installation of girders for the new Bandra-Dharavi bridge, marking a crucial juncture in the Rs 204 crore reconstruction project. This expansion to 10 lanes aims to alleviate traffic congestion between the Bandra Kurla Complex (BKC), Dharavi, and Mahim Causeway, key commercial and residential areas in Mumbai.
The Mithi River widening initiative, the project's larger framework, is progressing in phases to ensure ongoing traffic flow. Phase I saw the construction of a new bridge alongside the existing structure on its western side, already completed. Current Phase II sees the erection of another bridge on the eastern side, with construction underway.
Post completion of both new bridges, the third and final phase will involve dismantling and reconstructing the existing bridge. The girders for the second bridge have already arrived at the site, with assembly work in full swing. Once erected, the additional infrastructure is anticipated to significantly reduce congestion and enhance connectivity.
Written by urgent.news from Free Press Journal's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.