Changing City: BKC-Dharavi travel to get quicker, girder launch set to start on Mithi River bridge
The Mumbai civic body, Brihanmumbai Municipal Corporation (BMC), is set to commence girder launching on the new bridge connecting Bandra and Dharavi over the Mithi River. This development aims to enhance Mithi's flow and improve connectivity between the suburbs and South Mumbai. The new bridge is part of the second phase of a Rs 204 crore project, originally launched to widen the existing bridge to 10 lanes.
The Mithi River basin widening project, which secured final approvals in 2019, involves demolishing the existing bridge, built nearly 50 years ago, to make way for a newer, wider bridge. The project is being executed in three phases. The first phase saw the construction of a new bridge abutting the existing structure on the west side.
In the second phase, another new bridge is being developed on the east side of the existing structure. Once the final phase is complete, traffic will be diverted to the two new bridges, followed by the demolition of the old structure, which will later be redeveloped.
A senior official from the BMC revealed that while the project was initially conceptualized as per the Chitale committee's recommendations to widen the Mithi River, it will also provide smoother traffic for commuters traveling between suburban areas and South Mumbai. The girders for the new bridge have arrived at the site, and their assembly is currently underway.
Written by urgent.news from The Indian Express's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.