Blackout prompts questions over ElectraNet's recent $300m network upgrade
The blackout that left nearly 24,000 Eyre Peninsula properties in the dark comes only three years after ElectraNet finished a $300 million upgrade that promised more reliable power to the region.
On Thursday, the Eyre Peninsula in South Australia experienced a blackout following a severe weather event. ElectraNet, the state's sole provider of electricity transmission services, had recently invested $300 million in a network upgrade, believing it would enhance power reliability. However, the $300 million project, completed in March 2023, failed to prevent the blackout.
The downed transmission towers were located in Wharminda, on a 270-kilometre transmission line between Port Lincoln and Cultana. ElectraNet CEO Simon Emms had claimed the upgrade would provide a more secure and reliable power supply, but the incident has sparked questions over the effectiveness of the upgrade. The Australian Energy Regulator (AER) approved ElectraNet's $280 million investment in the project in September 2020.
The blackout has reignited discussions about the cost-effectiveness of such upgrades and the need for further investment, with some residents expressing dissatisfaction over the failure of the recently completed transmission line within just a few years of its construction.
Written by urgent.news from ABC News AU's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.