Hospital Kapar dijangka operasi seawal Jun 2027, bantu surai kesesakan HTAR

Menteri kesihatan berkata, pembangunan projek berjalan ikut jadual, dan setakat 20 Okt lepas, kemajuan fizikalnya berada pada tahap 96.26%.

Hospital Kapar dijangka operasi seawal Jun 2027, bantu surai kesesakan HTAR

Menteri Kesihatan Dzulkefly Ahmad announced that Hospital Kapar will commence operating on a phased basis from June next year, according to the Klang Healthcare Minister. The KKM is monitoring progress in the construction of the hospital as a long-term solution to alleviate congestion at Hospital Tengku Ampuan Rahimah (HTAR) Klang.

He stated that the Major Specialist Hospital will operate with a capacity of 312 beds in addition to 17 specialty departments, including a special isolation ward, an infectious operating theater, and biosafety level 3 (BSL-3) autopsy rooms.

As of October 20, the physical progress of the Hospital Kapar project stood at 96.26%, while the financial progress reached 85.07%. The project is on schedule with no deviations and is projected to commence operations from June 2027. The population of Kapar alone is estimated to be around 320,000 people, which includes 1.2 million residents in Klang, according to the minister after visiting HTAR today.

Written by urgent.news from Free Malaysia Today's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.

Other reports of this story

Every outlet that reported this, and when →

Read the original at freemalaysiatoday.com →

More in World

More from Wednesday 18 November →