Los Montesinos floating solar plant gets regional go-ahead
The €748,248 project will install 1,344 solar panels on two irrigation ponds in Lo Vigo, reducing the footprint of the original farmland proposal by about 41 per cent. The Valencian regional government has approved plans for a floating solar power plant on two irrigation ponds in Los Montesinos. The project, proposed by Operativa 2000, will […] The post Los Montesinos floating solar plant gets…
The Valencian regional government has given preliminary approval for a €748,248 floating solar power plant project in Los Montesinos. Operativa 2000, the developer, will install 1,344 solar panels on two irrigation ponds, reducing the project's footprint by 41%. The plant will store excess electricity in two 125-kilowatt battery units.
The project, initially proposed in July 2021, was revised in October 2025 to use existing ponds and add battery storage. The Generalitat's landscape assessment found the redesign would preserve farmland and reduce visual impact. The plant will connect to the I-DE distribution network and must maintain agricultural use of the land.
Maintenance crews are restricted from using products that could contaminate the water. The project received a favourable environmental assessment with conditions to protect irrigation water. The developer has 11 months to complete construction and may apply for an extension.
Written by urgent.news from The Leader's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.