Government cannot terminate Pan Borneo contracts at will, warns Nanta
KUALA LUMPUR, Nov 17 — The government could face legal action and damage claims if it arbitrarily termi...
Datuk Seri Alexander Nanta Linggi, Works Minister, cautioned that the government risks legal repercussions and claim damages if it arbitrarily ends contracts awarded to contractors for the Sabah Pan Borneo Highway (LPB) project without adhering to proper procedures and legal requirements. Nanta emphasized that contractors possess specific rights, including the ability to request an Extension of Time (EOT) when delays are attributable to factors beyond their control, such as land acquisition compensation delays.
He explained that if the state Department of Lands and Surveys fails to settle land acquisition compensation, contractors can't access the site due to landowners' refusal. In such scenarios, contractors are entitled to seek an extension of time. Nanta underscored that terminating contracts without compliance with governance and legal obligations could invite legal action, leading the government to bear the associated costs.
He highlighted the impact of political interference at the local level on the land acquisition process, noting that directives often faced interference from local leaders, leading to delays and prolonged waiting periods. Additionally, the minister addressed the challenges associated with relocating utility infrastructure, such as cables and water pipes.
Regarding the LPB Phase 1 project, which the 2020 Auditor-General's Report criticized for its slow progress, Nanta noted that Phase 1B had commenced in September 2024 and achieved 26% physical and 23% financial progress. However, Phase 1A, which commenced earlier, faced significant setbacks, with physical progress reaching 90% and four packages fully completed.
The problematic packages under Phase 1A, particularly Packages 1 and 2 near the Sarawak border, were identified as contributors to overall progress slowdown. Nanta indicated that the Works Ministry acknowledged the Auditor-General's Report without defensiveness and had reorganized Public Works Department personnel to enhance project administration and execution.
The ministry aimed to complete the entire Pan Borneo Highway by 2030, guided by four key strategies: a Completion Recovery Plan, ensuring land readiness, controlling costs for Phase 1B, and using an Audit Compliance Tracker to address the 13 findings within stipulated timelines. Moreover, Nanta mentioned that the Sarawak-Sabah Link Road (SSLR) project would include constructing the first tunnel in Borneo, exceeding two kilometers in length, connecting northern Sarawak to Sabah via Lawas and bypassing Brunei.
The SSLR would be built to lower R3-standard rural road specifications but would enhance connectivity to interior areas of both states.