Nscale i brev til regjeringen: – Det haster

En uke før strømstansen for datasentre skrev selskapet at de vurderer å bidra til…

Nscale i brev til regjeringen: – Det haster

Nscale, an AI company in Norway, has several data center projects that require power, and these projects are currently in the queue with Statnett, Norway's power transmission system operator. In October, Nscale's head Per Øyvind Voie requested a meeting with political leaders in the energy department to discuss matters such as power generation.

A week later, Voie followed up again after not receiving a response. E24, a Norwegian news outlet, obtained a copy of a letter from Voie and found it to be quite urgent. Voie mentioned that Nscale is in dialogue with most actors considering large-scale power generation in Norway and plans to contribute to triggering such projects.

However, Voie also noted that there is a possibility of a moratorium for further development of AI centers in Norway, which means a temporary halt or suspension of activities. The moratorium was introduced by Statnett on its own accord, and Energy Minister Terje Aasland confirmed this during a press conference. Statnett stated that this action is taken to ensure the safe operation of the power system, as the sector is overwhelmed with requests for more electricity.

Nscale has asked E24 several questions, including why there was a rush to meet, if they have had a meeting, if they believe the power demand to Statnett is a moratorium, and if they are now moving away from considering these power projects. Stian Jenssen, a spokesperson for Nscale, stated that in a period of many changes in the industry, it is important for Nscale to have an ongoing dialogue with relevant authorities and other affected parties, including Statnett and others.

Nscale has multiple reservations in Statnett's queue and is committed to contributing to the triggering of new power generation and grid capacity. However, for this to be possible, predictable conditions are a prerequisite, according to Jenssen. The Ministry of Energy informs E24 that political leadership has not had a chance to meet with Nscale.

Earlier, the British company Nscale, where Aker is the largest shareholder, was mentioned in DN. The company has a total of eight data center projects in Norway, with a collective power need of approximately 2,700 megawatts. This information was obtained from an E24 mapping they conducted. Three of these projects are seeking connection before August 1, 2027.

Written by urgent.news from E24 Norway's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.

Read the original at e24.no →