Blr airport road curbs: Check Blue Line update

Bengaluru's Namma Metro Blue Line, a 58-km project connecting Central Silk Board to Kempegowda International Airport (KIA), is set to become fully operational by March 2028, three months later than initially planned. The delay is due to construction and material procurement issues, primarily along the Outer Ring Road (ORR) and the Hebbal-Kempapura stretch.

The Hebbal-KIA segment is targeted for completion by September 2027, while the KR Pura-Hebbal section, including Nagawara, is slated for completion between December 2027 and March 2028. The Central Silk Board-KR Pura stretch has already entered the advanced stage, with commercial operations expected to commence by mid-2027.

Motorists traveling on Ballari Road, especially those heading towards or departing from Kempegowda International Airport (KIA) via Hebbal, will face traffic restrictions and diversions for the next 18 months while the Bangalore Development Authority (BDA) constructs a four-lane elevated corridor measuring around 1.7km between Anandnagar near Hebbal and Mehkri Circle.

To facilitate smooth vehicular movement, including for emergency vehicles, motorists are advised to utilize alternative routes while traveling between Hebbal, the airport, and the city.

The project has encountered several obstacles, including the need to build infrastructure for four Metro tracks between Hebbal and Kempapura, a first for Namma Metro's mainline network. This challenge involves constructing a specialized three-pier portal structure along a nearly 1-km stretch to support all four tracks. Additionally, heavy traffic, utility shifting, land constraints, and difficulties in developing stations along the busy corridor have complicated construction along the ORR.

Another hurdle is the restrictions imposed by Tamil Nadu on the transportation of stone materials. These restrictions have made it difficult for contractors working on the corridor to procure construction materials, affecting several other infrastructure projects in Bengaluru as well. Karnataka Truck Owners and Agents Association president GR Shanmugappa stated that over 40,000 tonnes of stone were being transported to the city before the ban, with 600 to 700 truck owners affected.

The restrictions, imposed by Tamil Nadu on July 27 for an initial period of three months, have remained in place since then.

Written by urgent.news from The Economic Times's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.

Read the original at economictimes.indiatimes.com →