Pan Borneo Highway: Works Ministry to address audit findings, improve project delivery, says Nanta
KUALA LUMPUR, Oct 8 — The Ministry of Works (KKR) is taking seriously the 13 findings in the 2026 Auditor-General&...
The Ministry of Works in Malaysia is addressing the 13 audit findings from the 2026 Auditor-General’s Report (LKAN) on Phase 1 of the Sabah Pan Borneo Highway (LPB) project, according to Works Minister Datuk Seri Alexander Nanta Linggi. The report identified issues such as project delays, cost increases, planning weaknesses, and non-compliance with regulations.
As of August 25, only four out of 35 work packages have been completed, with physical progress at varying levels for different phases. The delays are attributed to factors like the shift from the Project Delivery Partner (PDP) model to the conventional method, the Covid-19 pandemic, land acquisition issues, utility relocation, and contractor performance.
The cost increase is due to factors such as project extension, scope changes, construction contract prices, and unresolved land and utility issues. In response, the Ministry of Works has directed relevant officers to attend administration and contract management courses to improve their skills. Additionally, the Sabah LPB Steering Committee, established in November 2024, continues to enhance monitoring through its site visit programme, with recommendations for improved coordination among state agencies.
Brief written by urgent.news from Malay Mail's own syndicated text. Machine-written — may contain errors; check the original before relying on it.
This story
This is one outlet's version. Read the fullest account.
- Pan Borneo Highway: Works Ministry to address audit findings, improve project delivery, says Nanta malaymail.com
- Defence minister delivers pro-Canada message in Alberta, highlights $8B in funding globalnews.ca
- Federal defence minister McGuinty delivers pro-Canada message in Alberta, highlights $8B in funding cbc.ca