Why only 7 land officers tasked to survey 706km corridor, asks MP

Isnaraissah Munirah Majilis says 12 private valuation firms were only appointed much later despite the project's scale.

Why only 7 land officers tasked to survey 706km corridor, asks MP

The Auditor-General's report has sparked questions regarding the allocation of manpower for the survey of the Sabah section of the Pan Borneo Highway. Isnaraissah Munirah Majilis, an MP from Warisan-Kota Belud, expressed her concern over the fact that only seven land officers were initially assigned to oversee a 706km corridor. She questioned whether one officer could manage such a vast distance, as 88% of the work on the Sabah section of the highway remains unfinished, despite the project beginning in 2015.

Isnaraissah also pointed out that only 12 private valuation firms were appointed in December last year, making it unclear why the situation was allowed to persist until then. The former deputy minister argued that if the government was aware of the manpower shortage from the outset, they should have taken steps to address it. She also inquired whether the federal government had raised this issue with the Sabah government, given that federal funds were involved.

The report also highlighted significant weaknesses in planning and execution, with only four out of 35 work packages completed, nine classified as sick projects, and 13 behind schedule. The highway was initially planned to be completed by the end of 2021.

Rewritten by urgent.news; may contain errors — check the original.

Other reports of this story

Every outlet that reported this, and when →

Read the original at freemalaysiatoday.com →

Report a problem with this story

More in World

More from Wednesday 7 October →