Petra explains Sungai Golok project cost rise to RM601m in response to A-G report
PUTRAJAYA, Oct 6 — The Sungai Golok Integrated River Basin (PLSB) project in Kelantan saw its contract value incre...
The Sungai Golok Integrated River Basin (PLSB) project in Kelantan has seen its contract value increase from RM198.02 million to RM601.20 million due to adjustments made to the project scope based on technical requirements and conditions during implementation. The Ministry of Energy Transition and Water Transformation (Petra) cited upgrades to the Security and Development (KESBAN) road, modifications to the spillway structures, bridge construction, and pump house design as key changes to ensure the infrastructure meets functional, safety, and long-term durability requirements.
Additionally, project implementation was affected by on-site technical constraints, including utility relocation, land acquisition, and coordination of construction drawings. Petra acknowledged weaknesses identified in the Auditor General’s Report (LKAN) 2/2026 and committed to addressing the matters raised, implementing follow-up actions by the Department of Irrigation and Drainage (DID) to improve consultant management and clarify responsibilities and accountability.
Brief written by urgent.news from Malay Mail's own syndicated text. Machine-written — may contain errors; check the original before relying on it.
This story
This is one outlet's version. Read the fullest account.