TCN Restores Kainji–Birnin Kebbi 330kV Transmission Line
The Transmission Company of Nigeria (TCN) has announced that the 330kV Kainji–Birnin Kebbi Single Circuit Transmission Line, which was taken out of service following the collapse of Tower 367 on
The Transmission Company of Nigeria (TCN) has restored the 330kV Kainji–Birnin Kebbi Single Circuit Transmission Line to service, following its collapse on September 7, 2026. The line was taken out of service after the tower, known as Tower 367, fell. TCN restored the line by erecting an Emergency Restoration System (ERS) tower at the site in Yauri.
The restoration process included the dismantling and decommissioning of the collapsed tower, aligning and preparing the conductors and skywire, erecting the ERS tower, and completing other associated works to ensure safe line operation. TCN engineers worked continuously to expedite the restoration and return the line to service as safely and swiftly as possible.
The company expressed gratitude for the patience and understanding shown by electricity consumers in the impacted areas during the outage and reaffirmed its commitment to maintaining a stable and reliable transmission network.
Written by urgent.news from This Day's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.