Sabah Pan Borneo Highway: Only 4 of 35 packages complete after a decade
THE Sabah Pan Borneo Highway Phase 1 project remains largely incomplete more than a decade after it was planned, with only four of its 35 work packages completed as of March 31, the Auditor-General’s Report 2/2026 has found. Auditor-General Datuk Ser...
Despite being planned over a decade ago, the Sabah Pan Borneo Highway Phase 1 remains largely unfinished, as revealed by the Auditor-General’s Report 2/2026. Only four out of the 35 work packages have been completed, representing a mere 11.4% of the 706-kilometre project that was originally budgeted at RM567 million. The remaining 31 packages, valued at RM16.319 billion, are still under construction.
Of the 31 ongoing projects, nine are considered sick, 13 are behind schedule, while nine have surpassed their planned timelines. The audit also uncovered significant management irregularities, such as approvals for Variation Orders surpassing the authorized limits by RM513.99 million, and delays in claiming RM41.37 million in utility relocation costs.
In the Sarawak Pan Borneo Highway project, 10 work packages have been fully completed, while Work Package 11 is 99.9% finished as of March 31, but the overall project's success cannot yet be evaluated as the project has not been fully completed.
Written by urgent.news from The Vibes's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.
This story
This is one outlet's version. Read the fullest account.
- General : Audit Report Flags Weaknesses In Pan Borneo Highway, Flood Mitigation Projects bernama.com
- A-G flags weak execution, violations in Pan Borneo Highway project in Sabah freemalaysiatoday.com
- AG Report: 88pc of Sabah Pan Borneo Highway incomplete after 11 years nst.com.my
- Audit Dept flags continued delays, RM514m in unauthorised variation orders on Sabah Pan Borneo Highway malaymail.com