Now, build Mambilla
The landmark judgment delivered on September 17, 2026, by the International Chamber of Commerce (ICC) in Paris has brought immense relief to Nigeria in its protracted dispute with Sunrise Power and Transmission Company Limited over the Mambilla Plateau Hydroelectric Power Project. For nearly two decades, the country faced the threat of paying $3.38 billion to […]
On September 17, 2026, the International Chamber of Commerce in Paris ruled in Nigeria's favor in its long-standing dispute with Sunrise Power and Transmission Company Limited regarding the Mambilla Plateau Hydroelectric Power Project. The decision vindicated Nigeria's position and avoided a costly settlement of $3.38 billion that had been threatening the nation.
The controversy dates back to 2003 when then-Nigerian Minister of Power, Olu Agunloye, awarded the project contract to Sunrise without the proper authorization from then-President Olusegun Obasanjo. The irregular award delayed the project's execution by China Gezhouba Group Corporation and prevented full-scale work from starting in 2007.
Despite some progress in clearing the site, the arbitration battle between Nigeria and Sunrise halted the project's development. The Mambilla Power Project, which could generate over 3,000 megawatts of electricity, was on hold as the dispute went through several rounds of failed negotiations and aborted settlements before reaching the ICC tribunal in Paris.
Nigeria's predicament goes beyond the Mambilla project, as similar cases like Process and Industrial Developments Limited's claimed $11 billion gas-processing facility and Global Infrastructure Holdings Limited's $10-14 billion claimed damages for the Ajaokuta Steel Company have exposed the risk of crippling liabilities from dubious contracts.
These cases highlight the importance of vigilant oversight in public procurement to safeguard national resources. Furthermore, the corruption involved in these cases, as revealed by the Economic and Financial Crimes Commission, has undermined Nigeria's institutions and eroded public trust in governance. The ICC ruling on the Mambilla project is a significant step forward for Nigeria, allowing the government to finally move forward with the 3,050MW hydroelectric project and address the critical issue of power supply in the country.
Written by urgent.news from Daily Trust's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.