New Jersey hits data center powering Microsoft Copilot with $1m fine after drone expose 62 secretly-installed gas generators

DataOne data center responsible for Microsoft's AI accused of running 62 natural gas generators without any permits.

New Jersey hits data center powering Microsoft Copilot with $1m fine after drone expose 62 secretly-installed gas generators

New Jersey has imposed a $1.07 million fine on a data center powering Microsoft's AI system for illegally operating 62 gas generators without proper permits. The discovery came after a local farmer photographed the campus while golfing, prompting an investigation using thermal drones. The state found that only 45 out of the 62 generators were actively running at the time of the drone's deployment.

The Air Pollution Control Act mandates both reconstruction permits for installation and operating certificates for running generators. Neither were obtained for all 62 units, leading to the hefty fine. Microsoft was using these generators to provide off-grid electricity, which is beneficial for reducing strain on local infrastructure and energy costs.

However, the CO2, NO2, and CO emissions from the generators are a concern. DataOne, the company responsible, disagrees with the fine but must apply for the necessary air permits within 45 days. Microsoft is in communication with the Department of Environmental Protection regarding the findings and the transition to fuel cells.