Estimated cost of Irish Rail control centre rises

Irish Rail's National Train Control Centre (NTCC) project, that includes a new traffic management system, is now projected to come up to €57m over-budget.

Estimated cost of Irish Rail control centre rises

The National Train Control Centre (NTCC) project for Irish Rail, encompassing a new traffic management system, is now estimated to exceed its initial budget by €57 million. This over-budget situation has caught the attention of Comptroller and Auditor General Seamus McCarthy in his report accompanying the National Transport Authority's 2025 financial statements.

Initially, the project, which aimed to include the construction of a new train control centre at Heuston Station, refurbishment of the existing centre at Connolly Station, and a new train traffic management system, was projected to be completed by March 2025 with a budget of €148 million. However, McCarthy's report reveals that the actual forecasted cost of the project now ranges between €175 million and €205 million.

The primary driver of this increased cost is delays and challenges encountered during the delivery of the traffic management system component, which has necessitated an extension of the project timeline. The National Transport Authority acknowledges taking proactive steps to address these issues, collaborating with key stakeholders to implement mitigation measures and revise delivery arrangements.

To date, €148.3 million has been spent on the project by the end of 2025, with an additional €12.2 million committed for future accounting periods. The board of Irish Rail had previously reduced the value of its investment in the NTCC by €50 million due to the ongoing financial strain, much of this reduction attributed to the extensive spending on the traffic management system.

McCarthy's report sheds light on various cost-related aspects of the project, including €6.96 million spent on storing and servicing new electric buses in storage, which were delayed due to challenges in providing charging infrastructure. The storage and servicing costs for 2025 alone amounted to €1.27 million. McCarthy notes that the temporary storage costs for electric buses stemmed from procurement challenges and planning consent issues beyond the control of the National Transport Authority and operators.

Despite these setbacks, the project remains a crucial component of Ireland's rail network, with completion of the Heuston Station train control centre completed in 2022.