One Migration, Start to Finish

New to this? Read the eight stages first. That page tells you which stage you are in and what to do about it. This page shows all eight happening on one real-shaped job, so it makes more sense second. By the end of this page you will have seen a whole migration run, start to finish. You will know what was sent on the day each stage closed, who signed it, what it cost when the client asked for…

A migration is comprised of eight stages, with each stage concluding at a gate. A gate represents a checkpoint with an owner and a written response: someone agrees in writing that the stage is complete, allowing the next stage to begin. Two emails, one from gate 1 and another from gate 6, are presented in full. The engagement involves moving 1,482 client records, 58,740 visits, and 6,310 documents, some of which are paper.

Kickoff occurred on 23 February 2026, and go-live was scheduled for 3 August 2026. Mid-cutover, representing the actual move, occurred mid-way through the process. The client had named their Data Owner, J. Okafor, to address any data-related questions. The kickoff and scope stage took place from 24 February to 13 March. The client identified J. Okafor as the Data Owner, and the exclusion list was established, removing records from before 2019 from the migration.

Gate 1 was signed by A. Reyes, the Client PM, on 13 March. The profiling stage occurred from 16 March to 1 April. Two significant findings emerged during profiling: 1,204 client records lacked a date of birth, which was a required field in the target system, and the service type was a free text field with multiple variations. The profiling report and the decisions made from it were signed by A. Reyes on 1 April.

The field mapping stage took place from 2 April to 1 May, during which the client requested scheduling history to be migrated. This request added three more weeks to the timeline and two weeks of effort. The client ultimately decided to hold the original go-live date, with scheduling history becoming phase two. Gate 3 was signed by J. Okafor on 1 May.

Written by urgent.news from Dev.to's reporting — not their text. Machine-written — may contain errors; check the original before relying on it.

Read the original at dev.to →

More in Tech

Dev log #17 From 16-bit TUIs to p2p Hardening: A 227-Commit Week

A high-output week focused on shipping GitBanner 1.3.0, hardening WebRTC and DHT layers in py-libp2p, and archiving kad-monitor with a proper demo harness.

  • GitBanner shipped 1.3.0 release with 16-bit type system
  • py-libp2p hardening focused on IP subnet diversity and /sdp server security
  • Kad-monitor demo harness completed with simulation and dashboard

More from Sunday 16 August →