  "id": 22088695,
  "title": "Sabah Electricity scrambles to reconnect East Coast after Ranau tower collapse, eyes Dec 2 recovery",
  "url": "https://urgent.news/2026/11/27/sabah-electricity-scrambles-to-reconnect-east-coast-after-ranau-tower",
  "topic": "world",
  "section": "World",
  "published": "2026-11-27T01:00:00.000Z",
  "source": {
    "name": "Malay Mail",
    "slug": "malay-mail-malaymail",
    "url": "https://www.malaymail.com/news/malaysia/2026/11/27/sabah-electricity-scrambles-to-reconnect-east-coast-after-ranau-tower-collapse-eyes-dec-2-recovery/244934"
  },
  "original_language": "en",
  "account": "KOTA KINABALU, Nov 27 — Sabah Electricity aims to fully restore transmission lines to East Coast Sabah within six days, targeting a complete grid recovery by Dec 2 following the collapse of transmission tower T313 in Ranau. The tower collapse, detected at 6.04am, severed two circuits running from the West Coast to the East Coast, disrupting power to eight districts and 153,599 registered consumers. Sabah Electricity Chairman Datuk Saadiah Aziz said the six-day timeframe allows for the transportation of equipment and erection of temporary towers at a safe site near the collapsed tower. The current power supply to the East Coast is generated by local power stations in Tawau and Sandakan, supported by mobile generators, including for essential facilities like hospitals, schools, and police stations. To mitigate load-shedding effects, Sabah Electricity has merged grid lines and implemented rotational rationing. Telecommunications restoration, coordinated by the Malaysian Communications and Multimedia Commission (MCMC), is being conducted alongside Sabah Electricity and service providers, with 1,196 cellular sites and fixed lines affected as of 12:52pm. Mobile generators and Starlink satellite connectivity are being used to ensure telecommunications continuity. Sabah Electricity has also provided hotlines and WhatsApp support for inquiries and verification, dismissing claims of a two-week power outage as false.",
  "summary": "KOTA KINABALU, Nov 27 — Sabah Electricity has set a six-day timeframe to restore the 275-kilovolt (kV) electricity trans...",
  "key_points": [
    "Sabah Electricity aims to restore East Coast grid by Dec 2",
    "Tower collapse severed 2 circuits, affecting 153,599 consumers",
    "Mobile generators and Starlink used to maintain telecoms"
  ],
  "editors_take": null,
  "illustration": null,
  "coverage": {
    "outlets": 1,
    "also_reported_by": []
  },
  "ai_generated": true,
  "disclaimer": "Summaries, key points and the editor’s take are written by software from other outlets’ reporting and may contain errors — always check the linked original."
}