  "id": 21077766,
  "title": "MahaRERA Pulls Up Developer For Delayed Flat Possession, Orders Handover Within 60 Days",
  "url": "https://urgent.news/2026/11/21/maharera-pulls-up-developer-for-delayed-flat-possession-orders",
  "topic": "world",
  "section": "World",
  "published": "2026-11-21T16:26:39.000Z",
  "source": {
    "name": "Free Press Journal",
    "slug": "free-press-journal",
    "url": "https://www.freepressjournal.in/mumbai/maharera-pulls-up-developer-for-delayed-flat-possession-orders-handover-within-60-days"
  },
  "original_language": "en",
  "account": null,
  "summary": "The Maharashtra Real Estate Regulatory Authority (MahaRERA) has taken action against Ekta Parksville Homes Pvt Ltd for delayed flat possession, ordering the developer to hand over possession of two flats within 60 days and pay statutory interest. The orders were passed on November 18, 2026, following two separate complaints filed by homebuyers. In the first complaint, the developer was blamed for delays due to various factors, including the change of planning authority, stop-work notices, and Covid-19. However, MahaRERA rejected these claims, stating that the agreed possession period had already expired in August 2018. In the second complaint, the developer offered possession on May 21, 2019, citing a six-month grace period and extensions. Despite this, MahaRERA directed the developer to hand over the flat within 60 days and pay interest for the delay.",
  "key_points": [],
  "editors_take": null,
  "illustration": null,
  "coverage": {
    "outlets": 1,
    "also_reported_by": []
  },
  "ai_generated": true,
  "disclaimer": "Summaries, key points and the editor’s take are written by software from other outlets’ reporting and may contain errors — always check the linked original."
}